By Andrea Shalal-Esa
Gilmore, director of
operational test and evaluation for the U.S. Defense Department, has
long been critical of the $392 billion F-35 Joint Strike Fighter, the
Pentagon's costliest weapons program, and the latest report is no
exception.
Lockheed
is developing the F-35 for the Marines, Air Force and Navy, and eight
countries that helped fund its development: Britain, Canada, Australia,
Norway, Italy, Turkey, Denmark and the Netherlands. Israel and Japan
have also ordered the jet.
An official at South Korea's arms procurement agency, the Defense Acquisition Program Administration said any delays beyond an intended 2018 delivery date would be "problematic". Seoul has said it would buy 40 of the F-35s, though still has to finalize this order.
A senior Japan Defense Ministry official said: "We can do nothing but ask the JPO (Joint Program Office) to speed up the program." Tokyo plans to buy 42 of the stealth fighters, with the first four due for delivery by March 2017.
The Australian Defence Force declined to comment. Australia is one of the largest international buyers with plans for up to 100 F-35s.
WASHINGTON
(Reuters) - A new U.S. Defense Department report warns that ongoing
software, maintenance and reliability problems with Lockheed Martin
Corp's F-35 stealth fighter could delay the Marine Corps' plans to start
using its F-35 jets by mid-2015.
The
latest report by the Pentagon's chief weapons tester, Michael Gilmore,
provides a detailed critique of the F-35's technical challenges, and
focuses heavily on what it calls the "unacceptable" performance of the
plane's software, according to a 25-page draft obtained by Reuters.
The
report forecast a possible 13-month delay in completing testing of the
Block 2B software needed for the Marine Corps to clear the jets for
initial combat use next year, a priority given the high cost of
maintaining current aging warplanes.
The report, due to
be sent to Congress this week, said the aircraft is proving less
reliable and harder to maintain than expected, and remains vulnerable to
propellant fires sparked by missile strikes.
Air
Force Lieutenant General Chris Bogdan, the Pentagon's F-35 program
chief, said in a statement to Reuters that Gilmore's report was
factually accurate but did not reflect concerted efforts under way by
his office and industry to address software, reliability and maintenance
issues.
"The basic design of
the F-35 is sound, and test results underscore our confidence in the
ultimate performance that the United States and its international
partners and allies value so highly," Bogdan said. "Of course, we
recognize risks still exist in the program, but they are understood and
manageable."
Bogdan said he
remained confident that the F-35's initial combat capability would be
ready in time for the U.S. Marine Corps next year, and cited a series of
successful weapons tests done late last year. He said the program was
about halfway through developmental testing after completing 1,153
flights and accomplishing more than 9,000 test objectives in 2013.
An official at South Korea's arms procurement agency, the Defense Acquisition Program Administration said any delays beyond an intended 2018 delivery date would be "problematic". Seoul has said it would buy 40 of the F-35s, though still has to finalize this order.
A senior Japan Defense Ministry official said: "We can do nothing but ask the JPO (Joint Program Office) to speed up the program." Tokyo plans to buy 42 of the stealth fighters, with the first four due for delivery by March 2017.
The Australian Defence Force declined to comment. Australia is one of the largest international buyers with plans for up to 100 F-35s.
The
F-35 program, which began in 2001, is 70 percent over initial cost
estimates, and years behind schedule, but top U.S. officials say it is
now making progress. They have vowed to safeguard funding for the
program to keep it on track.
OTHER CRITIQUES
Earlier
this week, the nonprofit Center for International Policy said Lockheed
had greatly exaggerated its estimate that the F-35 program sustained
125,000 U.S. jobs to shore up support for the program.
Both
reports could provide fresh fodder for critics of the F-35 program,
including backers of Boeing Co, which is hoping to sell the U.S. Navy
more of its F/A-18 fighter jets.
But
Lockheed Chief Executive Marillyn Hewson told reporters on Thursday
that she saw continued support for the F-35 from the U.S. government,
Congress and foreign allies.
"There's no question ... that we need the F-35. It brings a very important, unique capability for our nation," she said.
Lockheed
spokesman Michael Rein said Gilmore's report confirmed the F-35 was
meeting or exceeding flight test goals, and the company would continue
to tackle issues as they arose.
"The
challenges identified are known items and the normal discoveries found
in a test program of this size and complexity," he said.
Gilmore's
report acknowledged the F-35's progress in 2013 on flight testing,
despite government furloughs and two fleet-wide groundings. But it said
the program was still struggling to integrate the plane's "mission
systems," or sensors, weapons and other equipment needed for use in
military operations.
The
current software generated too many nuisance warnings and resulted in
poor sensor performance. Further work on software had been slowed by
testing required to validate earlier fixes, the report said.
It
said Lockheed had delivered F-35 jets with 50 percent or less of the
software capabilities required by its production contracts with the
Pentagon.
The computer-based
logistics system known as ALIS was fielded with "serious deficiencies"
and remained behind schedule, which affected servicing of existing jets
needed for flight testing, the report said. It said the ALIS diagnostic
system failed to meet even basic requirements.
But
the most immediate concern involved the Block 2B version of the
software that must be completed in order for the Marines to start using
the jets from July 2015.
"Initial
results with the new increment of Block 2B software indicate
deficiencies still exist in fusion, radar, electronic warfare,
navigation, electro-optical target system, distributed aperture system,
helmet-mounted display system, and datalink," the report said, noting
the problems could delay efforts to complete Block 2B development and
flight test.
The report cited
projections that the 2B software would not be completed until November
2015, 13 months later than planned. This would delay release to the F-35
fleet until July 2016, a year after the Marines want to start using the
jets.
It said there is also
little margin for any weight growth, and the airplane's increased use of
electrical systems makes it vulnerable to lightning and missile
strikes.
Bogdan said extensive
studies had showed the plane's radar-evading capabilities, advanced
sensors, ability to fuse data, advanced countermeasures and electronic
attack equipment greatly reduced the chance that it would be hit by
enemy fire.
(Reporting by Andrea Shalal-Esa; Editing by Doina Chiacu and David Gregorio)
No comments:
Post a Comment